Cutting factory energy cost in Zimbabwe: motors, compressed air and drives
Motors use most of the power in a factory. How they are sized, controlled and looked after decides most of your electricity bill.
In this article
- The unit of analysis is the motor system, not the motor
- Measure before you decide
- Motors: size, efficiency and repair policy
- Compressed air: the most expensive utility
- Variable speed drives and the cube law
- Connect the measures to the three parts of the bill
- The regulatory dimension
- A sensible order of work
- How AVEX GRID helps
Key points
- Motors use about 53% of the world's electricity and about 72% of the electricity used in industry, says the International Energy Agency.
- The same body estimates that 20 to 30% of motor system energy could be saved with measures that are cost-effective.
- Compressed air is the costliest energy in a plant. Leaks often waste a fifth to a third of what the compressors make.
- For fans and pumps, power falls with the cube of speed. Slowing the machine by a fifth cuts its power by about half.
- The order of work matters: reduce the load, then size the equipment, then control it, and only then consider replacement.
Industrial energy saving is often shown as a long list of unrelated measures. For a factory it is easier to see it as one problem. You have a large number of electric motors. Each motor drives a load, and each runs at some part of its capacity. The International Energy Agency's technology collaboration on Electric Motor Systems (EMSA) reports that motor systems used about 53% of the world's electricity in 2023. In industry they used roughly 72%. So a factory that understands its motor systems understands most of its electricity bill.
This article follows the energy from the meter to the machine. It explains why so much is lost on the way. It then sets out the measures that win it back, in the order an engineer would apply them. The principles are the same in Harare, Bulawayo or a plant elsewhere in the region. But in Zimbabwe the economics are shaped by three things. The tariff, has a maximum-demand charge. The supply is unreliable. And plants depend heavily on imported equipment.
The unit of analysis is the motor system, not the motor
A motor is only one part of a system. The system also includes the electrical supply, the control gear, the mechanical transmission and the machine being driven. Energy is lost at every stage. The motor itself may be 90 to 96% efficient at its best operating point. But a belt drive, a gearbox, a damper that throttles a fan, or a valve that throttles a pump can lose far more. For this reason the biggest savings usually lie after the motor, in the way the load is controlled, and not in the motor itself.
The EMSA programme estimates that you can save between 20 and 30% of the energy used by motor systems, and that this is cost-effective. That is the equivalent of roughly a tenth of all the electricity in the world. The saving does not come from one technology. It comes from a sequence of improvements:
- remove demand that serves no purpose;
- match the equipment to the load;
- control speed and output to follow what the process needs from hour to hour.
Source: IEA 4E Electric Motor Systems Annex, policy brief (2025)
Measure before you decide
Every credible efficiency programme starts with measurement. Put loggers on the main incomers and on the main motor control centres. Run them for at least two weeks, including a full production cycle. They show the base load that runs when the plant is idle. They show the daily and weekly pattern. And they show the peaks that set the maximum-demand charge. The same data point out three problems: motors that run lightly loaded, equipment that runs when nothing is being produced, and loads that start together and create avoidable peaks.
Many plants find that their night-time or weekend load is a large share of their daytime load. This is the cheapest saving available, because it needs no new equipment. Compressors, extraction fans and pumps are simply switched off when they are not needed. Automatic controls make the saving permanent, because it no longer depends on people remembering to act.
Motors: size, efficiency and repair policy
A motor is most efficient when it is loaded to between roughly 60 and 100% of its rating. It also has its best power factor there. Power factor shows how much of the power you draw is actually useful. A figure of 1.00 is perfect, and motors, transformers and welders pull it down. A motor that runs at 30% load, as many oversized motors do, has a lower efficiency and a much poorer power factor. It draws reactive power. This is the power that motors and transformers use to build their magnetic fields. It does no useful work, but many tariffs charge for it on your bill. It also adds to the losses in the plant's cables and transformers.
The international standard IEC 60034-30-1 defines efficiency classes from IE1 to IE4. IEC is the International Electrotechnical Commission, which writes international standards for electrical equipment. IE3 is a high efficiency class, and IE4 is higher still. Many countries now require IE3 as the minimum for new motors. A higher class costs a little more to buy. But that extra cost is small next to the electricity the motor uses over its life. For a motor that runs several thousand hours a year, that electricity can be many times the purchase price. Three rules follow:
- When a motor fails, replace it with the correctly sized, high-efficiency unit. Do not rewind it out of habit.
- For large motors that run long hours, compare the cost of a rewind with the cost of a new motor. Include the efficiency that is lost in rewinding.
- Do not replace a motor that is working well and is correctly loaded. The saving does not justify the cost.
Compressed air: the most expensive utility
Compressed air is convenient, safe and flexible. It is also very inefficient. A compressor is a machine that squeezes air to drive tools and machines. A large share of the electrical energy that goes into it leaves as heat. Only a small part ends up as useful work at the tool. The United States Department of Energy estimates that compressed air systems use about 10% of the electricity in manufacturing in that country, and 30% or more in some plants. Its guidance says leaks can often waste 20 to 30% of a compressor's output. A systematic leak programme can bring the losses below 10%.
A sound approach has four steps.
- Find and repair leaks with an ultrasonic detector. Record them, and repeat the survey from time to time, because new leaks appear as fittings and hoses age.
- Lower the system pressure to the lowest level the processes need. Each extra unit of pressure raises the power the compressor uses.
- Match compressor capacity to demand with sequencing or variable-speed control, so that machines do not run unloaded.
- Stop using compressed air where something cheaper will do. Blowing down surfaces or cooling are examples. A low-pressure blower or a fan can do these jobs with a fraction of the energy.
Variable speed drives and the cube law
The affinity laws govern fans and centrifugal pumps. They say that flow is proportional to speed, pressure to the square of speed, and power to the cube of speed. This is the basis of the strongest savings in motor systems. A fan running at 80% of full speed delivers 80% of the flow, but needs only about half of the power. Throttling a damper or a valve to reduce flow does the opposite. The motor keeps running at nearly full speed, and the energy is wasted as pressure drop.
A variable speed drive therefore pays where the demand for flow changes during the day. This is the case in cooling water systems, dust extraction, ventilation and many pumping duties. It pays far less on loads that run at constant full output. It also pays less on positive-displacement machines, where the link is closer to a straight line. The load profile, and not the equipment catalogue, tells the engineer where a drive is justified. Drives also reduce starting current and mechanical stress. This lowers the peak that sets the maximum-demand charge. They can also improve power factor at the motor terminals.
Calculated from the fan affinity laws (power varies with the cube of speed). Source: US Department of Energy, motor systems
Connect the measures to the three parts of the bill
A manufacturing customer pays for energy in kilowatt-hours. They also pay for the highest demand in kilovolt-amperes during the billing period. In many cases they pay a charge for poor power factor too. Motor measures act on all three:
- Switching idle equipment off reduces the energy.
- Staggering starts, and using soft starters or drives, reduces the peak.
- Right-sizing motors and fitting correctly sized capacitor banks improve the power factor.
We discuss these links in our articles on maximum-demand charges and power factor correction.
The regulatory dimension
The Electricity (Energy Management) Regulations, SI 122 of 2026, set rules for larger users. A facility with installed capacity of 100 kVA or more is a designated facility. The kVA figure is the size of the load on the supply, including the part that does no useful work. Transformers and generators are rated in kVA. A designated facility must have an energy-management policy, a licensed audit at least every three years, an investment plan and annual reporting.
A plant that has already logged its loads, listed its motors and repaired its air system will find these duties much easier. The data the regulations ask for already exists. Our ten-step guide sets out the sequence.
A sensible order of work
The measures above give the best returns when you apply them in a deliberate order.
- Measure, and switch off what is not needed.
- Repair compressed air leaks and lower the pressure.
- Correct the sizing and control of the largest fans and pumps. Add drives where the load varies.
- Replace motors at failure with the right-sized, high-efficiency unit.
- Last, correct the power factor and flatten the peak. By then the load is smaller, so the equipment can be sized correctly.
Working in this order stops you buying capacity or correction that you no longer need once the load has been reduced.
How AVEX GRID helps
- Load profile and walkthrough audit. We log your main feeds and motor control centres, and give you a ranked, costed list of measures.
- Motor, compressed air and drive review. We check the sizing, leaks, controls and where a drive pays, using your own data.
- SI 122 readiness. We organise the records, the policy structure and the investment plan that the regulations require.
What AVEX GRID can take off your hands
AVEX GRID is an engineer-led energy consultancy in Zimbabwe. We do the technical work that turns an energy investment into a plant that is licensed, connected, financed and performing, whether you are a local operator or an investor overseas.
We quote fixed prices after a free scoping call and reply the same working day.
Frequently asked questions
Which saving usually pays back fastest?
Switching idle equipment off and repairing compressed air leaks. Both need little capital and appear on the next bill.
Is a high-efficiency motor worth the extra cost?
For motors that run long hours, yes. The electricity used over the motor's life is many times its purchase price, so a small gain in efficiency is worth more than the extra cost.
Where does a variable speed drive not pay?
On loads that run at constant full output and on positive-displacement machines. The cube law that makes drives so effective on fans and centrifugal pumps does not apply to them in the same way.
Do I need an audit before I spend money?
A short audit with logging avoids spending on the wrong measure and prepares the data that SI 122 asks larger sites to keep.
Sources and notes
General information to help you plan. The rules that apply to your site are confirmed by AVEX GRID against the current gazetted text, ZERA and ZETDC as part of the work. The sources used are listed below.