ZERA Net-Metering Registration

Statutory Instrument 86 of 2018 lets businesses feed solar power back to the grid and earn credits from the utility, but the registration involves a lot of paperwork. We prepare the technical pack.

Share this service WhatsApp Email

In depth

Net metering in Zimbabwe, step by step: from design to the commissioning test

This article follows one grid-tied solar system from the first design to the day it is registered and metered. It adds to our wider guide to own-consumption solar and net metering. Here you get a practical sequence you can plan around.

01

What net metering means

A net-metered customer makes electricity on site, uses what is needed and sends any extra to the grid. A two-way meter records both flows. The utility sets the exported energy off against the imported energy in the billing period. You pay for the difference. Depending on the arrangement, you may carry a credit forward. The exact terms are in the regulations and the utility rules for your tariff class.

02

Stage 1: Design for the connection rules

The design must respect the capacity of your supply and the utility's technical requirements. The key items are the inverter ratings, the protection settings, the cable sizes and the point of connection. The design also decides how much of the energy you will use on site. That sets the value of the plant.

03

Stage 2: The technical file

  • A single-line diagram showing the array, the inverters, the protection and the point of connection.
  • Datasheets and certificates for the inverters and the panels.
  • The protection settings, including how the system behaves with anti-islanding.
  • A site layout and the contact details of your installer.

Read the full guide: Net metering in Zimbabwe, step by step: from design to the commissioning testAlso covered: Stage 3: Approval and agreement · Stage 4: Installation and metering · Stage 5: The commissioning test · Avoiding delays

What you get

Results you can take to your board or lender

Solar design ready to export

A system sized for your load, with the right protection, that meets the grid-connection rules before you buy equipment.

A complete application pack

Forms, single-line diagram, protection settings and commissioning papers, put together so nothing is missing.

Clear payback

A simple model of what you save and what you export. The assumptions are written down so your finance team can check them.

Deliverables

What lands in your inbox

  • Review of your site and load
  • Sizing and single-line diagram
  • Protection and grid-connection notes
  • Application document pack for the owner to file
  • Commissioning test checklist
  • Payback summary in plain language
Technicians checking string inverters and isolators on a commercial rooftop with solar panelsRooftop solar

Before the call

What to bring

Rough information is fine. This is what lets us scope and quote quickly.

  • Planned system size and equipment datasheets
  • Single-line diagram of the installation
  • Your ZETDC account number and latest bill
  • The installer or contractor details

How we work

From first message to finished work

  1. 1

    Brief

    A short call or message. Tell us about your site, your deadline and what is at stake. We reply within one working day.

  2. 2

    Scope & fixed quote

    We agree exactly what we will deliver, what we need from you, the timeline and a fixed price, before any work starts.

  3. 3

    Engineer & document

    We study your data, test the options and write the report or application, with every assumption stated.

  4. 4

    Hand over & support

    You get the finished package and a walk-through. We stay available while it is reviewed, approved or built.

Questions we hear

Before you book

Do you submit the application for me?

We prepare the technical content and the document pack. The owner or installer files with the utility and the regulator. We help you answer any questions that come back.

How long does it take?

The utility and regulator set their own timelines. On our side, a typical small commercial system pack takes one to two weeks once we have your bills and site details.

Are the rules still the same?

Rules change. We work from the latest published text and tell you where the registration or sign-off must come from a licensed party.

Standards & tools our work is prepared to
IEC 60909 IEEE 1584 IEEE 519 IPMVP ISO 50001 ETAP ZERA Grid Code

Talk to an AVEX GRID consultant

Have a project in mind, or want a second opinion on a quote you have received? Send us a short message and we will reply within one working day.