A technician checking an automatic power-factor correction cabinet with capacitor stages and a controller
Power quality9 November 2026·11 min read

Power factor correction in Zimbabwe: stop paying for reactive power

Low power factor is one of the electricity costs you can fix once and keep fixed. But if you do not measure your plant first, the fix can go wrong.

In this article
  1. What power factor means
  2. The three kinds of power, in plain words
  3. How it reaches your bill
  4. How big a bank do you need?
  5. Which capacitor bank?
  6. A trap for solar sites: your power factor can get worse
  7. How a correction project should run
  8. The harmonic trap
  9. The money case
  10. Prove it: what to record after commissioning
  11. What to ask a supplier before you buy
  12. Common mistakes
  13. How AVEX GRID helps

Key points

  • Power factor shows how much of the power you draw is actually useful. Motors, transformers and welders pull it down.
  • A low power factor means extra charges on your ZETDC bill, and it also pushes up your kVA demand, so you can pay twice.
  • Capacitor banks are the usual fix. In our example a 153 kvar bank costs about US$4,600 and pays back in under eight months.
  • Solar can make your power factor worse at the meter, because you import less useful power while your motors still need the same reactive power.
  • Measure first, size second, check third. If your plant has variable-speed drives, the capacitors must be the detuned type.
中文摘要 · CHINESE SUMMARY

津巴布韦功率因数补偿:不再为无功电量付费

  • 功率因数是有用功率(kW)与电网必须提供的总功率(kVA)之比。电机、变压器和焊机会拉低功率因数。
  • 根据2023年12月1日起生效的ZERA批准电价表,ZETDC在无功电量超过有功电量33%(对应功率因数约0.95)时收取无功电费(2020年旧规为48%)。
  • 功率因数低还会抬高kVA需量,因此可能被重复收费:一次是无功电费,另一次是需量电费。
  • 电容器组是常用方案。有变频器的工厂必须使用串联电抗(失谐)电容器组,否则可能发生谐振并损坏设备。
  • 先测量,再选型,最后验证。短期的数据记录成本远低于损坏一组电容器的代价。
  • AVEX GRID 提供测量、选型与验证服务(可远程分析数据,英文沟通)。

联系方式:WhatsApp +7 900 131 7406,邮箱 inquiries@avexgrid.com。

If a factory runs many motors, its power factor is probably lower than the plant manager thinks. Power factor shows how much of the power you draw is actually useful. A figure of 1.00 is perfect. Motors, transformers and welders pull it down, and a low figure costs you extra. This guide explains what power factor is in plain terms and how it shows on a Zimbabwean bill. It also explains how a correction project should be done. It is written for plant, mine, farm and building managers, and for the investors who budget their running costs.

What power factor means

Think of a glass of beer. The liquid is the useful power (kW) that does the work. The foam is reactive power). Reactive power is the power that motors and transformers use to build their magnetic fields. It fills the glass but does no work. The whole glass is the apparent power (kVA). That is the size of the load on the supply, including the part that does no useful work. The cables, transformers and the utility network must carry all of it. Power factor is the liquid divided by the whole glass. A value of 1.0 is all liquid. A value of 0.80 means a fifth of the glass is foam.

Source of low power factorWhy
Lightly loaded induction motorsThey draw nearly the same magnetising current whether loaded or not
Transformers running well below ratingFixed magnetising losses dominate
Welders and arc furnacesLarge, fluctuating reactive draw
Fluorescent and older discharge lightingInductive ballasts

The three kinds of power, in plain words

Your plant draws three things at once. They sit on different lines of your bill, so it pays to know which is which.

NameUnitIn plain wordsWhere you meet itRule of thumb
Active powerkWThe part that does the workYour energy (kWh) chargekW = kVA × power factor
Reactive powerkvarThe foam: needed by motors, but does no workThe reactive charge (kvarh) when it is too highCapacitors supply it on site
Apparent powerkVAThe whole glass: what cables and transformers must carryYour demand charge, and the rating on every transformer and generatorkVA = kW ÷ power factor
Worked exampleA load of 100 kW and 75 kvar is 125 kVA, not 175. They do not add like plain numbers. At a power factor of 0.80, a 500 kVA transformer can supply only 400 kW.

Four confusions that cost money

  1. kVA is not kW. Kit sized in kW alone can still be overloaded in kVA. A 500 kVA transformer gives you 400 kW at a power factor of 0.80, and 475 kW at 0.95.
  2. Low power factor makes your cables work harder. At 0.80 the current is 25% higher than at 1.00, and the heat lost in the cables is about 56% higher. At 0.95 the extra loss is only about 11%.
  3. Low power factor is not a loss inside the motor. The motor still does its job. The cost is on the cables, the transformer and your bill.
  4. A capacitor bank cannot fix everything. It cancels reactive power. It does not remove the distorted current described below.

When your drives distort the current

Variable-speed drives, rectifiers, LED drivers and solar inverters draw current that is not a smooth wave. That distortion lowers your true power factor on top of the reactive power. For example, a plant with a 0.95 power factor and 30% current distortion has a true power factor of about 0.91. A capacitor bank can lift the first number but not the second. Harmonics also heat transformers and can damage the capacitors themselves. That is why we measure them first.

How it reaches your bill

The tariff schedule approved by ZERA and effective from 1 December 2023 says that the Zimbabwe Electricity Transmission and Distribution Company (ZETDC) charges US$0.052 per kvarh for reactive energy above 33% of active energy. That share matches a power factor of about 0.95. The 2020 leaflet used 48%, or about 0.90, so older advice is out of date. We read the rule and the rate from your own bill, because tariffs change.

There is a second effect. Maximum demand is often billed in kVA. Take the same 100 kW of useful load:

125 kVAdemand at a power factor of 0.80
105 kVAdemand at a power factor of 0.95
20 kVAdemand removed, before any reactive charge is avoided

So a power factor below target raises the demand charge. It may also add a reactive-energy charge. Both show on the bill, which is why correction usually pays back quickly. Our tariff guide shows how to read the lines.

Power factor against the ratio of reactive to active energyPower factor (1.00 is ideal). The red point is the ZETDC charge threshold, 48%
0.600.700.800.901.000.900.640%20%40%60%80%100%120%Reactive energy as a share of active energy

Calculated as 1 divided by the square root of (1 + ratio squared). The vertical axis starts at 0.60. Source: AVEX GRID calculation; threshold from the ZETDC tariff notice published by the Commercial Farmers' Union.

How big a bank do you need?

Size it from measured data, not from the nameplate. The rule is simple: take your real power in kW and multiply it by the gap between your present power factor and your target. Take a plant that draws 528 kW at a power factor of 0.88 and aims for 0.97:

Worked exampleThe gap between 0.88 and 0.97 works out to a factor of 0.289 (from standard tables). So 528 kW × 0.289 is about 153 kvar of capacitors. At the calculator's indicative US$30 per kvar for a standard bank, the hardware is about US$4,580.
Capacitors needed to reach 0.97kvar for a 528 kW plant, by starting power factor
264 kvar
PF 0.80
195 kvar
PF 0.85
153 kvar
PF 0.88
123 kvar
PF 0.90
76 kvar
PF 0.93

Calculated as kW times (tan of the present angle minus tan of the target angle). Source: AVEX GRID calculation

The chart shows why you measure first. A plant that is really at 0.80, not 0.88, needs about 264 kvar. A bank bought for the wrong figure is either too small to remove the charge, or too large. If it is too large, it pushes the plant into leading power factor.

Which capacitor bank?

TypeSuitsWatch for
Fixed bankSteady loads that run all the timeOvercorrection at light load
Automatic stepped bankVariable loads: most factoriesController settings, contactor wear
Detuned bank, 7% reactorSites with drives, rectifiers or invertersTuned near 189 Hz on a 50 Hz supply
Detuned bank, 14% reactorHeavy harmonic content, especially the thirdTuned near 134 Hz; costs more
Active filterSevere, fast-changing harmonicsHigher cost; sized from measurements

A detuned bank has a reactor in series with each capacitor, which keeps it from resonating with the harmonics your drives make. That is the whole point: the bank helps your power factor without amplifying the distortion. A plain bank on a plant full of drives can resonate and fail within months.

A trap for solar sites: your power factor can get worse

Solar inverters supply real power. Your motors still draw the same reactive power from the network. So when solar reduces the real power you import, the ratio of reactive to active energy at the meter goes up. Take the same plant. If 200 kW of solar covers part of the daytime load, the grid supplies 328 kW and the same 285 kvar. The power factor at the meter falls from 0.88 to about 0.75. The reactive-to-active ratio rises from 0.54 to 0.87. That is well past the 0.33 allowance.

0.88power factor at the meter before solar
0.75power factor at the meter with 200 kW of solar running
87%reactive as a share of active energy, against a 33% allowance

The remedy is to size the correction after the solar. Or you can let the inverters supply reactive power, where the grid code and the equipment allow it. A solar study that skips this can turn a saving on energy into a new charge. Read the solar economics in is solar worth it together with this section.

How a correction project should run

  1. Read the bill. Note the billed demand, the reactive-energy line and the tariff class.
  2. Log the plant. Record voltage, current, power factor and harmonics at the main incomer. Do this for at least a week that includes your busiest shifts. IEC 61000-4-30 sets out the methods, and IEEE 519 sets the harmonic limits.
  3. Size the correction. The kvar you need comes from the measured kW and the gap between actual and target power factor. Allow for load growth, but do not oversize. An oversized bank pushes the plant into leading power factor and can cause overvoltage.
  4. Choose the type. Fixed banks suit steady loads. Automatic banks with stepped control suit variable loads. Detuned banks (capacitors in series with reactors) suit plants with drives, inverters or rectifiers.
  5. Verify after commissioning. Compare the logged power factor and the next bills with the prediction.

The harmonic trap

Variable-speed drives, solar inverters, UPS units and LED drivers push harmonic currents into your network. A plain capacitor bank can form a resonant circuit with the transformer and amplify those harmonics. The signs are blown capacitors, nuisance trips, overheated transformers and failed drives. Where harmonics are present, the bank must be detuned. You choose the tuning frequency from measurements. This is why correction should follow power-quality measurement, not come before it.

Do not buy a bank from a catalogueA supplier who sizes only from the bill cannot know whether your plant has harmonics. Ask for the measurement and the resonance check in writing.

The money case

On most bills, correction is the cheapest saving you can make. In the worked plant, the bank costs about US$4,580 and returns about US$30,359 a year at the official ZETDC rates. That is a simple payback of about two months. The saving comes from removing the reactive-energy charge and from the smaller kVA demand. An investor evaluating a plant can read it as a quick, low-risk saving on running costs. A manager can read it as the first action to take before larger projects.

US$4,580about 153 kvar of standard capacitors at US$30 per kvar
US$30,359saving a year in the worked plant
About 2 monthssimple payback; detuned banks cost more and pay back later

Prove it: what to record after commissioning

RecordBeforeAfter
Power factor at the main incomer, logged over a weekFrom the measurement campaignSame points, same shifts
Reactive-to-active ratio on the billLast 12 billsFirst 3 bills after commissioning
Billed demand in kVALast 12 billsFirst 3 bills after commissioning
Harmonic voltage and current distortionMeasured at the incomerMeasured again with the bank in service
Capacitor current and temperatureNot applicableAt commissioning and at the first service

If a supplier will not agree to be paid after the results are measured, ask why. The method for reading the bill is in how to read your ZETDC bill.

What to ask a supplier before you buy

  1. Which measurements was the size based on, and can I see them?
  2. Is the bank detuned, and what harmonic measurements justify the choice?
  3. What is the resonance check at the transformer and the incomer?
  4. How many steps does the controller have, and what is the smallest step in kvar?
  5. What protection and discharge arrangements does the bank include?
  6. What is guaranteed: the power factor, the reactive-energy charge, or only the equipment?

A supplier who answers with measurements and a written guarantee is selling a result. One who answers with a catalogue number is selling a box.

Common mistakes

  • Sizing from nameplate motor ratings instead of measured load.
  • Installing a bank on a site that later adds drives or solar inverters, without re-checking.
  • Ignoring the supply voltage: sites with high voltage put more stress on capacitors.
  • Skipping maintenance: capacitors age, and a bank that has lost steps stops correcting.

How AVEX GRID helps

  • Power-quality measurement and a harmonic assessment of the site.
  • Correction design with kvar sizing, detuning and protection, checked in ETAP.
  • Bill verification after commissioning, so the saving is shown on paper.

What AVEX GRID can take off your hands

AVEX GRID is an engineer-led energy consultancy in Zimbabwe. We do the technical work that turns an energy investment into a plant that is licensed, connected, financed and performing, whether you are a local operator or an investor overseas.

Feasibility and bankable studiesYield, load and hybrid models, and the technical file lenders and ZERA read.
Power-system engineering (ETAP)Load flow, short circuit, arc flash and protection studies for approvals and safe design.
Licence and PPA technical supportZERA licence documents, ZETDC connection studies, PPA technical schedules.
Owner's engineerDesign review, testing and commissioning on your side of the EPC table.
Tariff, audit and compliance workMaximum-demand and power-factor savings, readiness for energy-management rules.
Remote plus on the groundModelling for overseas teams, with an engineer in Zimbabwe for site, utility and regulator work.

We quote fixed prices after a free scoping call and reply the same working day.

Frequently asked questions

What is the difference between kW, kVA and kvar?

kW is active power, the rate of useful work. kvar is reactive power, which swings between source and load without doing net work. kVA is apparent power, the combination of the two: S is the square root of P squared plus Q squared. Cables, transformers and generators are rated in kVA because they must carry the current for the whole of it.

What does a power factor of 0.8 mean?

That active power is 80% of apparent power. The current is 25% higher than it would be at unity for the same useful power, and the loss in the cables is about 56% higher.

Will adding solar affect my power factor?

Yes. Solar supplies real power, so the real power you import falls while your reactive demand stays the same. The ratio of reactive to active energy at the meter rises and the power factor falls. Size the correction after the solar study.

What is a detuned capacitor bank?

A bank with a reactor in series with each capacitor step, tuned below the lowest harmonic the plant produces. A 7% reactor tunes the bank near 189 Hz on a 50 Hz supply, so it cannot resonate with the fifth harmonic at 250 Hz.

What is a good power factor?

Under the December 2023 ZETDC schedule the reactive charge starts below about 0.95. Many plants target 0.95 to 0.97 to avoid it and reduce kVA demand. Check the threshold in your own tariff.

Will power factor correction reduce my kWh?

Not much. It mainly reduces kVA demand, reactive-energy charges and some cable and transformer losses. The kWh you use for production stays the same.

Is a capacitor bank safe if I have variable-speed drives?

Only if it is detuned and checked against the measured harmonics. A plain bank can resonate with the drives and fail.

How long does correction take to pay back?

It depends on your bill. We calculate it from your demand, reactive charge and project cost after reviewing 12 months of bills.

Topics: power factor correction Zimbabwecapacitor bank sizingZETDC reactive energy chargereduce electricity bill Zimbabweharmonics and capacitorsindustrial energy savings Zimbabweenergy consultant Zimbabwe

Sources and notes

General information to help you plan. The rules that apply to your site are confirmed by AVEX GRID against the current gazetted text, ZERA and ZETDC as part of the work. The sources used are listed below.

DJ

Devine Tafara Javangwe is the founder and lead consulting engineer at AVEX GRID. He holds an MSc in Electrical Power Engineering (Southern Federal University, 2025), is a Professional Member of the Zimbabwe Institution of Engineers and an IEEE member.

About the practice · Contact

Is your plant paying for reactive power?

Send us your last three bills. We tell you whether correction is worth doing, what it would cost, and whether your plant needs a detuned design.