Sizing solar plus battery: the questions that decide the design and the cost
A battery is not just a bigger solar panel. It is a separate machine with its own job, and that job decides its size, cost and how it is controlled.
In this article
- Question 1: What is the battery for?
- Question 2: Which loads must stay on?
- Three terms, explained
- Question 3: How much energy and how much power?
- Question 4: How is the solar array sized?
- What each hour of backup costs
- Why solar alone does not keep the lights on
- Question 5: Which battery and which inverter?
- Question 6: What does the control strategy do?
- When a battery pays for itself: the diesel case
- Three designs, side by side
- Battery life and the replacement budget
- The sizing sheet to ask for
- Common mistakes
- How AVEX GRID helps
Key points
- Decide the job first: backup during power cuts, using solar in the evening, cutting peak demand, or a mix.
- A battery has two sizes: energy (kWh) for how long it can supply, and power (kW) for how much it can supply at once.
- At about US$320 per kWh, each hour of backup for a 15 kW load costs about US$6,000. Ask how long your power cuts really last.
- Compared with running a diesel generator, the whole solar-plus-battery package paid back in about 1.6 years in our example.
- You rarely need every load running through every power cut. A modest battery with sensible priorities is usually the cheapest answer.
A hybrid system combines solar panels, a battery, and the grid or a generator. The setup that suits a clinic is different from the one that suits a cold store or a mine camp. This article explains the questions an engineer asks. We list them in the order in which the answers shape the design.
Question 1: What is the battery for?
| Purpose | What it needs |
|---|---|
| Backup during power cuts | Power for the critical loads, and energy for the length of a typical power cut |
| Evening supply | Energy to carry the solar power into the hours after sunset |
| Peak shaving | High power for short periods, with modest energy. This cuts your highest demand |
| Less generator use | Energy and power to cover the loads the generator would carry |
One battery can serve more than one purpose, but each purpose adds a requirement. So name your first priority. Otherwise you may get a system that is large and expensive and still fails at the one job that matters.
Question 2: Which loads must stay on?
List every load and mark it as critical, important or flexible. A clinic's vaccine fridge and theatre lights are critical. A water pump is flexible, because it can run when the sun is high. This list is the most important input to the design. It cuts the battery size more than any change to the equipment.
Three terms, explained
Batteries are described by two numbers that are easy to confuse. Energy (kWh) sets how long the battery can supply a load. Power (kW) sets how large a load it can supply at once. A datasheet adds a few more terms.
| Term | In plain words | Why it matters to you |
|---|---|---|
| Usable capacity | The kWh you can really draw | Size from this, not from the label |
| C-rate | How fast it can deliver | A big load needs a battery that can supply that power |
| Round-trip efficiency | What you get back | About 90% for lithium. Plan on it |
Recharging sets the size of the solar array. To refill the battery in one day, the array must make the battery's usable energy, plus the losses, from a day's yield of about 4.5 kWh per kWp.
Question 3: How much energy and how much power?
The energy you need is the critical load multiplied by the hours it must run on battery. The power you need is the highest critical load running at one time. This includes the surge when motors start.
Calculated as load times hours divided by 0.9. Losses and ageing add margin; the real design uses an hourly model. Source: AVEX GRID calculation.
Question 4: How is the solar array sized?
The array has two jobs. It must supply the daytime load and recharge the battery. Say you want the battery full by the afternoon after a full discharge. Then the array must produce enough extra power over the day to refill it. If the extra power is too little, the battery is only partly charged when the next power cut starts.
What each hour of backup costs
Go back to the worked example: a 15 kW critical load, with a battery you may discharge to 80% of its rating. Each hour of backup needs 15 kWh of usable energy, which is 18.75 kWh of nameplate. The calculator's rough default for battery cost is US$320 per kWh installed. At that price, one hour of backup costs about US$6,000 of battery. The cost rises in a straight line. So ask yourself: is the last hour worth it?
Battery only; the inverter, protection and installation are extra. The US$320 per kWh figure is the calculator’s indicative default. Source: AVEX GRID calculation
Most sites find that the first two or three hours give most of the value, because most power cuts are short. The hours beyond that are better handled by a generator that starts only when it is needed. The honest design question is how long your power cuts really are, not how long they could be. Keep a log of the dates and lengths of power cuts over the past year. Your own records or ZETDC notices can supply it. This turns a guess into a number.
Why solar alone does not keep the lights on
Many people are surprised by this. A grid-tied solar plant with no battery switches off the moment the grid fails. This is a safety rule called anti-islanding. It protects line workers from power coming back into the line from your roof. If you need power during a power cut, you need a battery or a generator. You also need an inverter that can make its own supply. This is the difference between a system that only saves money and one that also protects your operations. Settle it with your supplier first.
Question 5: Which battery and which inverter?
- Chemistry. Lithium iron phosphate is widely used because it lasts many cycles and is safer. The choice also depends on the operating temperature, the warranty and whether service is available.
- Cycle life and warranty. A battery that charges and discharges daily needs a warranty stated in cycles and in years. Check the conditions attached.
- Inverter type. Hybrid and battery inverters differ in power rating, surge capacity and how they connect to a generator or the grid.
- Protection and monitoring. Correct fuses, earthing, ventilation and remote monitoring protect people and your investment.
Question 6: What does the control strategy do?
A controller decides when the battery charges and discharges. It also decides when the grid or generator steps in. A simple rule keeps a reserve for power cuts and uses the rest for daily savings. The rules are written down and tested when the system is commissioned. This makes sure the system behaves as designed.
When a battery pays for itself: the diesel case
Backup is insurance. A battery also earns its keep when it replaces diesel. The calculator's diesel case takes a site with a 180 kW load. A generator runs it 6 hours a day for 300 days a year. The generator burns 98,182 litres and delivers energy at about US$0.64 per kWh. This uses the diesel price at the October 2026 ZERA maximum of US$2.04 a litre. Now add solar and a battery to cover 40% of that energy. The picture changes.
| Value | |
|---|---|
| Solar array | 87 kWp, US$82,935 |
| Battery | 144 kWh, US$46,080 |
| Total investment | US$129,015 |
| Generator energy replaced | 129,600 kWh a year |
| Diesel avoided | 39,273 litres a year |
| Saving a year | US$81,418 |
| Simple payback | 1.6 years |
This is why a battery next to a generator is easier to justify than a battery next to a cheap grid connection. Generator energy is expensive, so replacing it saves a lot. Our guide to cutting diesel cost shows how to measure that cost first. Treat the numbers as a guide. The hourly model and your own prices decide the real result.
Three designs, side by side
| Site | Battery job | Sizing driver | Where the generator fits |
|---|---|---|---|
| Clinic | Keep the vaccine fridges, theatre and lights running | Critical load and length of power cuts | A last-resort backup for long power cuts |
| Cold store or packhouse | Carry the compressors through short cuts, and move solar power into the evening | Compressor starting current, and how long the room holds its cold | On standby, started by the controller |
| Day-shift factory | Cut the peak and ride through power cuts | Peak power, not energy | Rarely needed if the battery carries the load |
Battery life and the replacement budget
The battery is the part of a hybrid system that wears out with time. Cells age with use, deep discharge and heat. Many lithium iron phosphate products are rated at several thousand cycles. But the rating applies only under stated conditions. So read the warranty for the number of cycles, the capacity it guarantees at the end of life, and the temperature range it assumes. In your financial model, include a battery replacement part-way through the life of the plant, at a lower price than today. Show the result with and without it. A model that leaves out replacement makes the payback look better than it is.
The sizing sheet to ask for
- The load list, with each load marked critical, important or flexible.
- The power-cut record the design assumes: how often and how long.
- Usable and nameplate battery energy, and the depth of discharge assumed.
- Inverter continuous and surge power, with the motor starting current checked.
- The array size, and the weakest month in which it still recharges the battery.
- The control rules: reserve level, when the generator starts and stops, and charging priority.
- The cycle life and warranty conditions of the battery.
- Protection, ventilation, access and fire safety.
The rules for the solar part are in own-consumption solar and net metering, and the economics of the array alone are in is solar worth it for your factory.
Common mistakes
- Sizing the battery on the whole site load instead of the critical load.
- Forgetting the motor starting current when sizing the inverter.
- Buying a battery whose usable energy is well below the number on the label.
- Installing without a plan for ventilation, access and fire protection.
How AVEX GRID helps
- Load priority review and measured profiles, so the battery size rests on data.
- System design with single-line diagrams, protection and control rules.
- Commissioning and verification so the system performs as specified.
What AVEX GRID can take off your hands
AVEX GRID is an engineer-led energy consultancy in Zimbabwe. We do the technical work that turns an energy investment into a plant that is licensed, connected, financed and performing, whether you are a local operator or an investor overseas.
We quote fixed prices after a free scoping call and reply the same working day.
Frequently asked questions
How do I decide how many hours of backup to buy?
Start from the real power-cut record for your site, not the worst case you can imagine. Most power cuts are short. So the first hours give most of the value, and a generator can cover the rare long ones.
Do I need to replace the battery during the life of the plant?
Usually yes. Cells age with use, deep discharge and heat. Read the warranty for cycles and end-of-life capacity. Include a replacement in your financial model.
How long will a battery last in a power cut?
Divide the usable energy by the load. A battery with 60 kWh usable supplies a 15 kW load for about four hours. Real systems have losses, so the design adds a margin.
Can I run an air conditioner or a large motor on battery?
Yes, if the inverter and battery are sized for the running load and the starting surge. Motors need special care.
Does a bigger battery always cost more to run?
No. A battery has no fuel cost, but it has a limited number of cycles. So a larger battery that is discharged less deeply can last longer.
Can I add a battery later?
Often yes, if the inverter and the design allow it. It is cheaper to plan for growth at the start.
Sources and notes
General information to help you plan. The rules that apply to your site are confirmed by AVEX GRID against the current gazetted text, ZERA and ZETDC as part of the work. The sources used are listed below.