Cutting diesel cost at a Zimbabwean site: solar, storage and generator control
Diesel looks cheap until you work out what one kilowatt-hour from your generator really costs. Once you know that number, every saving can be tested against it.
In this article
- Calculate the cost of one kilowatt-hour
- What a generator kilowatt-hour really costs
- Why load matters
- Four ways to reduce diesel use
- A simple payback logic
- What to measure
- What the fuel curve really looks like
- The solar paradox
- An illustration with stated assumptions
- Controls, fuel losses and the behaviour of the set
- When the grid, not the generator, is the real problem
- Checks you can make this week
- How AVEX GRID helps
Key points
- The cost of a generator kilowatt-hour is fuel plus maintenance plus capital, divided by the energy it supplies. Fuel is usually the largest part.
- A generator is most efficient at a high share of its rated load. A lightly loaded set burns more fuel per kilowatt-hour.
- Four measures cut diesel use: match the set to the load, control how it runs, add solar for the day, and add storage.
- Every hour that the grid or solar can supply is an hour of diesel avoided, so the saving depends on how often the generator is called.
- Measure fuel and energy together for at least a month. Without that data, a saving cannot be proved.
Many sites in Zimbabwe run a diesel generator during power cuts, or as their main source. The generator keeps production going. But it is also one of your biggest controllable costs. This article shows how to work out the true cost of generator energy, and how to reduce it step by step.
Calculate the cost of one kilowatt-hour
Three inputs give the answer: the fuel price, the generator's fuel use for each kilowatt-hour, and the other costs of running it.
The regulator sets the fuel price, and it changes with the market. So always use the current price. The method does not change.
Calculated as price divided by 3.3. Maintenance and capital add to the full cost. Source: AVEX GRID calculation, using the worked example in this article.
What a generator kilowatt-hour really costs
Two numbers turn a generator's fuel bill into one figure you can compare with the grid. The yield is the kWh you get from each litre of diesel. The specific fuel consumption is the same thing the other way round, and engine datasheets use it. Add the fuel cost per kWh to your maintenance and capital cost per kWh and you have the true price of generator power.
| Item | Typical figure |
|---|---|
| Heat in one litre of diesel | about 10 kWh |
| Yield of a set at a good load | about 3.3 kWh per litre (33% efficient) |
| Fuel price (ZERA, October 2026) | US$2.04 per litre |
| Fuel cost per kWh | 2.04 ÷ 3.3 = about US$0.62 |
| Add maintenance and the cost of the set | The true cost is higher still |
Why load matters
A diesel engine turns fuel into electricity best when it works at a high share of its rated output. At low load, the fixed losses take a bigger share. So the litres you burn for each kilowatt-hour go up. A generator that is too big for the load wastes fuel on every run.
| Generator load | Effect on fuel use per kWh |
|---|---|
| Above about 60% of rating | Close to the best efficiency |
| 30% to 60% | Noticeably higher fuel use per kWh |
| Below 30% | High fuel use, and risk of engine problems if it persists |
Four ways to reduce diesel use
- Match the set to the load. Review the load profile. Where the load is much smaller than the set, a smaller unit works better. So do two units that share the load, because each runs closer to its best efficiency.
- Control how the generator runs. Automatic start, load sharing, and a controller that avoids long low-load running all cut wasted fuel. Regular maintenance keeps the engine efficient.
- Add solar for the day. A solar array supplies the daytime load, so the generator is needed less. The solar plant must be controlled so that it does not push the generator below its minimum load.
- Add storage. A battery carries the load through short outages and the evening. The generator then starts less often, and runs at a better load when it does. See our sizing guide.
A simple payback logic
A solar and storage addition may replace part of the generator energy at a lower unit cost. The yearly saving is then the kilowatt-hours it replaces, multiplied by the difference between the generator cost and the cost of the new energy. A proper study replaces this simple logic with an hour-by-hour model.
What to measure
- Fuel delivered and fuel used, from tank records or a flow meter.
- Generator running hours and the energy supplied, from the set's meter or a logger.
- The load profile of the site, including the hours of grid outage.
What the fuel curve really looks like
The figure of 3.3 kWh per litre in the example above is a good-load figure. Every generator maker gives a fuel consumption table. It shows litres per hour at 25, 50, 75 and 100 per cent load. Divide the output in kilowatts by the litres per hour, and you get the real kWh per litre at each point.
Studies of island power systems at the Sandia laboratories report that specific fuel consumption rises sharply below about 40% load. Generator makers such as Kohler warn that running below about 30% risks wet stacking. This is when unburnt fuel and carbon build up in the exhaust and the cylinders. The cost is double: more fuel for each kilowatt-hour, and more maintenance. Take a set rated at 80 kW that mostly serves 20 kW. It runs at a quarter of its capacity and wastes fuel, even if it never fails.
Take the real figures from your own plant. Get the maker's table. Log the kilowatts the set actually carries over a normal week. Then work out how many hours a month it spends below 40%. Often the answer is most of them. That points to one of three fixes: a smaller set, a second smaller set that takes the night load, or a battery to carry the base load.
The solar paradox
Adding solar to a generator site seems to cut diesel, and it does. But the Sandia work makes a point: solar can push the generator deeper into its inefficient range. Suppose a 100 kW set was carrying 60 kW, and a solar array now supplies 40 kW of that. The generator is now at 20 kW. It burns far more fuel for each kilowatt-hour than before.
So the design needs a rule. There are three choices. The controller can limit the solar output so the generator never falls below, say, 40% of its rating. A battery can take the surplus and let the generator switch off completely. Or you can install a smaller set. Each choice has a cost. So size the controller and the storage in an hour-by-hour model, and not by a rule of thumb.
An illustration with stated assumptions
Take a site whose generator carries a steady daytime load of 50 kW for 10 hours a day. That is about 500 kWh. At the fuel-only cost of US$0.61 per kWh from the example, that is about US$305 a day. Now suppose a 40 kWp array has a controller that handles the generator properly. The kWp figure is the rated size of a solar array under standard test conditions. A 100 kWp array can make up to about 100 kW in full sun. On an average day, this array delivers 180 kWh of useful daytime energy. That is based on roughly 4.5 kWh per kWp.
Over 250 generator-supplied days a year, that is 45,000 kWh. At US$0.61, the fuel it replaces is worth about US$27,000 a year, before the running costs of the solar plant. Now suppose the site runs the generator only as a backup for a few outages. Then the saving falls to the energy used on those days. This is why the number of hours the generator really runs is the first thing to measure. The model, the capital cost and the financing then decide the payback. That is the time the savings take to repay the cost of the project. It could be two years or ten.
Controls, fuel losses and the behaviour of the set
- Fuel losses. Fuel that is delivered and not used is a cost with no energy attached. Use a tank dip or a flow meter on the supply and return lines. Check it each month against the energy meter. This separates real consumption from leaks and theft.
- Maintenance. Clean air and fuel filters, correct injectors and a working cooling system bring back efficiency. A set that has lost 5% of its efficiency costs 5% more on every litre.
- Automatic start and load sharing. With two or more sets, a controller brings sets on and off as the load changes. Each then runs near its best point.
- Exercise at load. Running a standby set with no load for its monthly test is the surest way to cause wet stacking. Test it on a real load. Or use a load bank at the minimum the maker recommends.
When the grid, not the generator, is the real problem
In many Zimbabwean sites the generator runs because the grid is unreliable. So the cheapest kilowatt-hour is the one that stops the outage from starting. A site that loses power for a few hours at predictable times can sometimes shift loads. It can use a battery to ride through short cuts, or talk to the utility about the supply. Before you size any of the four measures, record the hours of outage and the load that was lost. A site that is off the grid for two hours a day needs a very different system from one that is off for twelve.
Checks you can make this week
- Read the running-hours meter and the fuel tank on the same day each week, and write down both.
- Find the nameplate rating and compare it with the highest load you have seen. If the peak is under half the rating, the set is too big.
- Ask the maker or supplier for the fuel consumption table at 25, 50, 75 and 100 per cent load.
- Over a month, compare fuel delivered with fuel used and energy supplied. A gap that you cannot explain is a loss to chase before any investment.
- Look at the service record. An overdue service is a cheap place to find a few per cent.
These checks cost almost nothing. They decide which of the four measures to study first.
How AVEX GRID helps
- Diesel cost baseline. A baseline is the starting point you measure savings against. We measure fuel and energy and work out your true cost per kilowatt-hour.
- Hybrid design. We size solar, storage and controls to the load and test the saving on an hour-by-hour model.
- Verification. We check the saving after commissioning, which is the testing that proves a new plant works as designed. So the result shows up in your fuel records.
What AVEX GRID can take off your hands
AVEX GRID is an engineer-led energy consultancy in Zimbabwe. We do the technical work that turns an energy investment into a plant that is licensed, connected, financed and performing, whether you are a local operator or an investor overseas.
We quote fixed prices after a free scoping call and reply the same working day.
Frequently asked questions
Why does a lightly loaded generator waste fuel?
Fixed losses take a larger share of the fuel at low load, so the litres per kilowatt-hour rise. Sandia studies report the rise below about 40% load, and makers such as Kohler warn of wet stacking below about 30%.
How many kWh does a litre of diesel produce?
A healthy generator at good load produces roughly three to three and a half kilowatt-hours per litre. Lightly loaded sets produce less. Your own records give the figure for your plant.
Can solar run with a generator?
Yes, with a controller that keeps the generator above its minimum load and limits solar output when needed.
Is it better to replace the generator or add solar?
It depends on the load and the hours the set runs. A load profile shows whether a smaller set, a second set, solar or storage gives the best return.
Does maintenance affect fuel use?
Yes. Clean filters, correct injectors and a good cooling system keep the engine efficient and lower the fuel per kilowatt-hour.
Sources and notes
General information to help you plan. The rules that apply to your site are confirmed by AVEX GRID against the current gazetted text, ZERA and ZETDC as part of the work. The sources used are listed below.