Energy audit rules in Zimbabwe: a plain-English readiness guide for larger electricity users
Zimbabwe's new energy rules make bigger electricity users do regular audits and report every year. Here is what each duty means and how to be ready.
In this article
Key points
- The Energy Management Regulations (SI 122 of 2026) cover sites with 100 kVA or more installed, and maximum demand customers of a distribution licensee.
- The duties are a policy, a licensed audit every three years, a three-year investment plan, action on the savings, and a yearly report.
- ZERA licenses audit, energy management and measurement work. A readiness review prepares you but does not replace the licensed audit.
- Savings must be measured, not assumed. IPMVP gives four ways to do this, and a good report says which one it used.
- Spend the next ninety days on data: bills, loads, metering, and who will own the programme.
Energy audits used to be optional. A company ordered one when its bills became painful. Now the Electricity (Energy Management) Regulations, SI 122 of 2026, make audits a repeat duty for larger electricity users. The regulations were gazetted on 31 July 2026. They also ask for a funded plan, and for proof that you are carrying it out. This guide lists the duties in the order a facility manager meets them. It also explains the measurement method that makes your savings believable.
Who is covered
The regulations apply to designated facilities. A site is designated in two cases. The first is when its installed capacity is 100 kVA or more. kVA is the size of the load on your supply, and transformers and generators are rated in it. The second is when the site is a maximum-demand customer of a distribution licensee. That means the utility charges it for the highest power it draws.
In practice this covers most factories, processing plants, mines, large farms and agro-processors. It also covers hotels, hospitals, campuses, large offices and shopping centres. If your bill shows a maximum-demand charge, assume the regulations apply to you. Then check the position against the gazetted text. We do this check for every site we work with, because the thresholds decide your dates.
What the regulations require
The duties fall into five groups.
First, an energy-management policy. It follows the ZWS ISO 50001 series. ISO 50001 is an international standard for managing energy step by step. Senior management endorses the policy and files it with the Zimbabwe Energy Regulatory Authority (ZERA), which licenses energy businesses and approves tariffs. An existing facility must file within twelve months of the rules starting. A new facility must file before it is connected.
Second, an energy audit. An energy audit is a survey of where a site uses energy and where it can save. It ends with a list of actions ranked by payback. A ZERA-licensed auditor must do it, following ISO 50002, at least once every three years. The report goes to ZERA within thirty days.
Third, an investment plan. You prepare it within three months of the audit. It lists each measure, its cost, its saving and its payback. Payback is the time the savings take to repay the cost. The plan also sets the order of delivery.
Fourth, action on the savings. You must carry out at least half of the savings found within three years of the plan.
Fifth, reporting. You send an annual implementation report within thirty days of year-end. You also send periodic energy-use returns. ZERA gives the facility a rating from class A, the best, to class E.
The regulations also set minimum energy-performance standards for common equipment. This includes motors, pumps, chillers, compressed-air systems, boilers and distribution transformers. You must also keep records of energy, fuel and water use for at least five years. If you keep one clean register of your consumption, every one of these duties becomes easier.
Source: Afriwise, SI 122 of 2026
Who may carry out the audit
ZERA licenses energy audit, energy management and measurement-and-verification work. A licence is official permission to do a regulated job. Doing this work without one is an offence. So a licensed party must do your audit.
This is where a readiness review fits. We do not present our work as the licensed audit. Instead, we review your bills and demand data and find the likely savings. We also organise your metering and records and prepare a phased investment plan. This makes the licensed audit faster, cheaper and more useful. We work alongside your licensed auditor or energy manager, and the final audit report is stronger because of the preparation.
Why the measurement method matters
Whatever kind of audit you do, a saving must be measured and not assumed. The accepted framework is the International Performance Measurement and Verification Protocol (IPMVP). It is the standard way to prove how much energy a project really saved. It does not force one single procedure on you. Instead, it gives four options. They differ in what you measure and where you draw the boundary.
| Option | What it measures | Typical use |
|---|---|---|
| A: retrofit isolation, key parameter | The key parameter of the retrofitted equipment is measured and the rest is estimated | Lighting replacement, where power is measured and hours are agreed |
| B: retrofit isolation, all parameters | All parameters of the retrofitted system are measured | A variable speed drive on a pump or fan, with continuous metering |
| C: whole facility | Meter data for the whole facility, adjusted by regression for weather and production | A programme of many measures, where the bill is the best evidence |
| D: calibrated simulation | A calibrated model of the facility, used where no baseline meter data exist | New buildings or deep retrofits |
A good audit report says which option it uses for each measure, and why. That lets a later auditor pick up the work and carry on. This matters because the regulations tie the programme to the share of savings you actually deliver.
How to prepare in the next ninety days
The preparation that pays most is not technical. It is collecting data and naming people. Work through this list.
- Collect twenty-four months of electricity bills. Note your supply capacity and your tariff class. The tariff is the price list for electricity: the rates per unit, per kVA and the fixed charges.
- List your three largest loads, such as compressors, chillers, pumps and large motors, with their nameplate data.
- Check whether the major loads have their own sub-meters. If they do not, plan the metering.
- Choose a senior owner for the programme and a person to act as energy manager. The regulations expect both.
- Confirm, against the gazette or with us, whether and when each duty applies to your site.
- Book a short readiness review, so you know your likely savings before the licensed audit begins.
Our guides on audit preparation and on SI 122 in ten steps go through the same sequence in more detail.
How AVEX GRID helps
- Coverage check. We confirm whether each of your sites is a designated facility and set the dates that apply.
- Readiness review. We review your bills and demand data, find likely savings and organise your metering and records.
- Investment plan and verification. We prepare a phased plan and the IPMVP method that proves the savings. Verification means an independent check that the reported figures are true. We work alongside your licensed auditor.
What AVEX GRID can take off your hands
AVEX GRID is an engineer-led energy consultancy in Zimbabwe. We do the technical work that turns an energy investment into a plant that is licensed, connected, financed and performing, whether you are a local operator or an investor overseas.
We quote fixed prices after a free scoping call and reply the same working day.
Frequently asked questions
Does a small factory have to comply?
It depends on installed capacity and on whether it is a maximum-demand customer. Sites with 100 kVA or more are designated facilities. We check each site individually.
Can AVEX GRID carry out the licensed audit?
No. The audit must be carried out by a ZERA-licensed auditor. We provide readiness support and prepare your data and plan so that the licensed audit is faster and more useful.
What is the difference between IPMVP options A to D?
They differ in what is measured and where the boundary is drawn, from a single retrofitted device to the whole facility or a calibrated model. The right option depends on the measure and the data available.
What should we do first?
Collect twenty-four months of bills, list the largest loads, check metering and name the person who owns the programme.
Sources and notes
General information to help you plan. The rules that apply to your site are confirmed by AVEX GRID against the current gazetted text, ZERA and ZETDC as part of the work. The sources used are listed below.