Reading a power purchase agreement: the technical schedules lenders look for
Lenders read a power purchase agreement (PPA) twice: once for the law and once for the engineering. The engineering reading decides whether the numbers can be trusted.
In this article
- The market a Zimbabwean PPA sits in
- Description of the facility
- Interconnection and grid requirements
- Metering
- Testing and commissioning
- Performance guarantees
- Operation and maintenance obligations
- Change, curtailment and outages
- What the guarantee is worth in money
- Deemed energy: who pays when the grid is down
- Payment security, currency and change in law
- Red flags, and what to do about them
- Ten questions to put to a developer before you invest
- A reviewer's checklist
- How AVEX GRID helps
Key points
- A PPA says who buys the power, at what price and for how long. The schedules say what must be delivered and how it is measured.
- At 9 US cents a unit, each 1% a 10 MW plant fails to deliver costs about US$15,000 a year.
- Zimbabwean solar PPAs run for about 25 years, some with Treasury guarantees. Payment security and change-in-law terms matter as much as the schedules.
- Focus on five schedules: the plant, the connection point, the metering, the testing and the performance guarantees.
- Have an engineer review the schedules before you sign. It costs far less than a dispute afterwards.
A power purchase agreement (PPA) is the contract under which a power producer sells electricity to a buyer. The buyer is often a utility or a factory. The headline terms are the tariff (the price) and the term (how many years). The technical schedules are often the longest part of the document. They decide how the contract works in practice. This guide explains the schedules in the order a technical reviewer reads them.
The market a Zimbabwean PPA sits in
First, the commercial picture. ZETDC is the utility that buys from most independent power producers (IPPs). Public reports show how recent deals were built. A 30 MW solar farm at Vungu was reported with a 25-year PPA under a solar buying pilot. A 15 MW plant at Hwange was reported with a 25-year term. A Victoria Falls solar project was reported on a shorter 10-year term with ZESA, the company that came before ZETDC. The Standard newspaper reported that government capped solar tariffs at 9 US cents per kWh for selected IPPs. The ZETDC tariff at that time was 12 cents. The same report said Treasury guaranteed the PPAs of ten selected projects, 271 MW in all, with more planned. It also said the government's implementation agreement covers currency conversion, an economic tariff and the PPA guarantee.
There are two more signposts. The ZIDA investment prospectus gives ZETDC's usual purchase price as roughly US$0.06 to US$0.12 per kWh. It also says that producers who sell directly to large users negotiate their own price. Direct sales travel over ZETDC's network under wheeling arrangements. A 2024 systems operations agreement between ZimGreenCo and ZETDC deals with wheeling of private power through the grid.
Different things measured on different bases: a generation cost, a purchase range, a cap and an average retail tariff. They show the neighbourhood, not a price to quote. Source: IRENA; ZIDA prospectus; The Standard; World Bank Zimbabwe National Energy Compact
Description of the facility
This schedule states the plant type, the rated capacity at the connection point, the equipment, the location and the date the plant is expected to start selling power. It must match the licence, the grid studies and the design. When these documents differ, lenders ask questions during their checks.
Interconnection and grid requirements
The interconnection schedule sets out the point where the plant connects to the grid and the voltage level. It also sets the protection and control requirements and the rules of the grid code. It refers to the studies that show the plant can connect safely. These studies check that voltage, fault current and stability stay within limits. A technical file with load-flow, short-circuit and protection studies supports this schedule.
Metering
The metering schedule says which meters decide the energy delivered. It also says where they are, how accurate they must be, and how they are tested and read. Every payment is based on the meter. So the wording must be exact.
Testing and commissioning
| Test | Purpose |
|---|---|
| Pre-commissioning checks | Safety, protection and equipment readiness |
| Capacity or performance test | Shows that the plant delivers its rated output under set conditions |
| Reliability run | Shows the plant runs steadily over a set period |
| Grid compliance tests | Show that the plant meets the grid code |
The schedule should state the test conditions, such as the sunlight and temperature ranges. It should say who witnesses the tests and what happens if a test fails. Vague test conditions often cause disputes at the end of construction.
Performance guarantees
Solar PPAs commonly use one of two measures. A production guarantee compares the energy delivered with the energy expected from the measured sunshine. An availability guarantee measures the share of time that the plant is ready to produce. Each measure needs a list of what is excluded, such as grid failures and events beyond anyone's control (force majeure). It also needs a method to calculate the shortfall.
Each point of guaranteed availability is about 88 hours a year; the definition of excluded events matters as much as the percentage. Source: AVEX GRID calculation.
The three terms behind the guarantee
A guarantee is only as clear as its wording. A PPA should state these three terms in full. The performance ratio follows the international standard IEC 61724-1.
| Term | In plain words | Who it protects |
|---|---|---|
| Availability | The share of time the plant is ready to run | The buyer, against a plant that is often down |
| Performance ratio | How much of the available sunshine becomes delivered power | The buyer, against a poorly built or kept plant |
| Deemed energy | Energy lost because the grid was down, not the plant | The developer, against grid failures |
Operation and maintenance obligations
This schedule sets the standards for running and maintaining the plant. It also covers the reports the owner must give and how fast faults must be fixed. Read it together with the operation and maintenance contract. What you owe the buyer should be matched by what the contractor owes you.
Change, curtailment and outages
- Who carries the cost when the grid is down or the buyer cannot take the energy?
- How is curtailed energy (power the plant is told to hold back) measured and paid for?
- How much notice is needed for planned shutdowns?
What the guarantee is worth in money
A guarantee only feels technical until you put a price on it. Take a 10 MW solar plant that yields 1,650 kWh per kWp a year. This is the figure our calculator uses for Zimbabwe. The plant produces about 16,500 MWh a year. At the capped 9 US cents per kWh reported for selected IPPs, that is US$1,485,000 of revenue. Every percentage point of output that the contract does not protect is worth about US$14,850 a year. That loss repeats every year for 25 years.
An illustration built from the calculator’s yield assumption and the capped tariff reported for selected IPPs, not a quotation. Source: AVEX GRID calculation
This is why lenders read the guarantee, the way sunshine is measured and the list of excluded events as closely as the tariff. If too much is excluded, the developer carries a loss the model never showed. If too little is excluded, the buyer pays for energy that the grid could not take.
Deemed energy: who pays when the grid is down
Sometimes the buyer cannot take the energy, because the line is down or the network is overloaded. The plant has not failed, but it earns nothing. Many international solar PPAs answer this with deemed energy. The energy the plant would have delivered is estimated from the measured sunshine and the plant's known availability. The buyer then pays for it as if it had been delivered. We did not find a published standard clause in Zimbabwe. So the answer sits in each contract.
The stakes are easy to see. Say a grid failure stops a 10 MW plant for 100 daylight hours at an average output of 5 MW. That loses 500 MWh. At 9 US cents per kWh, this is US$45,000. A PPA without a deemed energy clause leaves that loss with the developer, and with the lender behind them.
Payment security, currency and change in law
- Payment security. Ask what backs the buyer's promise to pay. The Treasury guarantees reported for selected IPPs are one form. Letters of credit and payment accounts are others. Check that the guarantee covers your PPA and the full amounts, not only the headline.
- Currency. The tariff currency decides a lot. So do whether you can convert what you are paid and whether you can send it abroad. Together they decide what an overseas investor really receives.
- Termination payments. If the PPA ends early because the buyer defaults or government acts, a formula should repay the debt. Read how the formula is built.
- Change in law. The rules are changing. A summary of the regulations gazetted on 31 July 2026 describes new export controls. They cap exports by generation licensees at 30% of available capacity. ZERA decides export applications within 45 days. A PPA signed before such a rule must say who carries its cost. Treat that summary as a pointer and read the regulations themselves.
Red flags, and what to do about them
| What you see | Why it matters | What to ask for |
|---|---|---|
| Capacity in the PPA differs from the licence or the grid study | Approvals and loans are tied to a number that does not match the contract | One agreed capacity, repeated in every schedule |
| No meter accuracy class or test method | Every payment depends on one meter reading | Named meters, accuracy class, calibration and a way to settle disputes |
| Guarantee with broad exclusions | The shortfall falls on the seller and is not seen in the model | A closed list of exclusions, each one defined |
| No deemed energy or curtailment compensation | The grid decides your income | Measured and paid compensation for energy the buyer cannot take |
| Test conditions described as "normal conditions" | Handover turns into a dispute | Sunlight, temperature, duration, witness and pass marks, all in numbers |
| Obligations to the buyer are not matched in the construction and maintenance contracts | You owe the buyer what you cannot claim back from the contractor | Back-to-back schedules |
Ten questions to put to a developer before you invest
- Which tariff applies, in which currency, and does it change with an index?
- What backs the buyer's payments, and has anyone claimed on it before?
- What does the guarantee measure, and how is the sunshine measured?
- Which events are excluded from the guarantee?
- Is there deemed energy for grid failures and curtailment?
- Who pays for grid upgrades if the connection study asks for them?
- What happens to the loan if the PPA ends early?
- Which approvals does the PPA depend on, and which do you already have?
- How does the PPA treat changes in the rules after signing?
- Has an independent engineer reviewed the technical schedules?
For the wider picture of investing in Zimbabwean solar, read developing a solar IPP and investing in the energy sector. To learn about the engineer who checks all of this for the owner, see what an owner's engineer does.
A reviewer's checklist
- Do the capacity, voltage and connection point match the licence and the studies?
- Are the meters, their accuracy and the test method defined?
- Are the commissioning tests clear, with conditions and pass marks?
- Is the performance guarantee measurable, with fair exclusions?
- Does what you owe the buyer match what the construction and maintenance contractors owe you?
How AVEX GRID helps
- Technical schedules drafted or reviewed, so they are measurable and match your studies.
- Grid and yield studies that back up the connection and guarantee terms.
- Owner's engineer support through testing, commissioning and handover.
What AVEX GRID can take off your hands
AVEX GRID is an engineer-led energy consultancy in Zimbabwe. We do the technical work that turns an energy investment into a plant that is licensed, connected, financed and performing, whether you are a local operator or an investor overseas.
We quote fixed prices after a free scoping call and reply the same working day.
Frequently asked questions
Is deemed energy standard in Zimbabwean PPAs?
We found no published standard clause. International solar PPAs often include it, and lenders usually ask for it. Settle the point in the draft, before you sign.
What tariffs have been reported for solar IPPs in Zimbabwe?
The Standard reported a cap of 9 US cents per kWh for selected solar IPPs against a then-current tariff of 12 cents, and a government prospectus gives a typical ZETDC purchase range of about 6 to 12 US cents. These are reported figures, so confirm the current position with ZERA and ZETDC.
Who guarantees ZETDC’s payments?
Reports describe Treasury guarantees for selected IPP projects. Whether a PPA carries one, and for what amounts, depends on that contract and the implementation agreement.
What is the difference between a production guarantee and an availability guarantee?
A production guarantee measures the energy delivered against the energy expected from the measured sunshine. An availability guarantee measures the share of time the plant is ready to run.
Who prepares the technical schedules?
The developer and the buyer normally draft them, with technical advisers on each side. An independent technical review before signing reduces disputes.
Can I use the same schedules for a private PPA?
The structure is similar. Private PPAs for own use or wheeling follow the licensing and wheeling terms that apply to that arrangement.
What do lenders ask for first?
They ask for the licence, the technical file with the grid studies, the PPA with its schedules, and the yield assessment.
Sources and notes
General information to help you plan. The rules that apply to your site are confirmed by AVEX GRID against the current gazetted text, ZERA and ZETDC as part of the work. The sources used are listed below.
- IEC 61724-1: photovoltaic system performance, monitoring (performance ratio)
- Sandia PV Performance Modeling Collaborative: performance ratio
- The Standard (print edition, 3 March 2024): Zim on the cusp of a green energy revolution
- Renewables Now: ZETDC signs 30 MW solar PPA
- ZIDA investment opportunities prospectus
- IRENA: Renewable power generation costs in 2024
- World Bank: National Energy Compact for Zimbabwe
- ZELA: How Zimbabwe has changed the rules of energy investment
- PwC Australia: EPC contracts in the solar industry
- IEC 61724: photovoltaic system performance
- Afriwise: Zimbabwe energy sector regulation
- ZERA: Zimbabwe Energy Regulatory Authority