How to develop a solar IPP in Zimbabwe: licence, PPA and what lenders check
Zimbabwe wants more private power and is signing 25-year contracts to get it. A licence is only the start; the real work is getting the plant built and paid for.
In this article
Key points
- The steps are a ZERA licence, a power purchase agreement (PPA) with ZETDC, proof of funding, a grid connection agreement, then financial close and construction.
- 25-year PPAs with ZETDC were signed in 2026, including a 30 MWac pilot (Vungu Solar) and a large plant in Mashonaland West.
- Licensing is moving faster than building. ZERA approved 61 generation licences in 2025, but the private capacity actually running is much smaller.
- Lenders want a technical file: an independent yield estimate, a grid impact study, land and permits, buyer risk and a bankable model.
- An owner's engineer on your side of the EPC table protects your value after financial close.
如何在津巴布韦开发光伏独立发电项目(IPP):许可、购电协议与贷款方审查要点
- 据报道,开发流程包括:向ZERA申请发电许可证、与国家电力公司ZETDC谈判购电协议(PPA)、落实融资证明、签署电网接入协议,然后进入融资关闭与建设。
- 2026年有报道称ZETDC与多个光伏项目签署了为期25年的购电协议,包括30兆瓦交流侧的Vungu光伏试点项目。
- 许可发放快于建设速度:据报道,ZERA在2025年批准了61份发电许可证,但实际运行的私营装机仍然有限。
- 贷款方通常要求提供:独立发电量评估(P50/P90)、电网影响研究、土地与环境许可、购电方信用风险分析,以及可融资的财务模型。
- 建议聘请业主工程师(Owner’s Engineer),在EPC合同谈判与施工阶段代表业主把关。AVEX GRID可为海外团队远程建模并在当地提供支持(英文沟通)。
联系方式:WhatsApp +7 900 131 7406,邮箱 inquiries@avexgrid.com。
Zimbabwe makes less electricity than it needs, and it has opened the door to private producers. Solar developers can now get licences, guarantees and long-term contracts. This guide explains the path in plain terms. It also covers what slows projects down and what lenders look for. It is written for developers, investors, and the lenders and advisers around them.
The market in brief
The Zimbabwe Energy Regulatory Authority (ZERA) reported that most licence applications were for solar systems that companies build for their own use. The part of the market that sells to the grid needs a PPA. Examples include a 30 MWac pilot (Vungu Solar) with a 25-year PPA signed with ZETDC in early 2026, a 100 MW solar-plus-storage project (Matshela Energy). There is also a 25-year agreement for a large plant in Mashonaland West (Sigma Solar Africa project, June 2026).
A licence is not a plant. Earlier ZERA figures showed far more licensed capacity than working capacity. The same reports note that one project took more than two years to get its licence before it could sign a PPA. Budget time and development money for that gap.
The licensed and operational counts come from different editions; most operating plants serve their own sites. Source: Chambers, Power Generation 2025 and 2026 guides
The development path
| Stage | What happens | What you need |
|---|---|---|
| 1. Site and concept | Land, sunlight, grid connection point and an early layout | Land rights; yield estimate; the nearest substation and its capacity |
| 2. Licence application (ZERA) | Apply for a generation licence; ZERA's board sits every quarter | Technical description, single-line diagram, proof you can fund it, and permits as required |
| 3. Grid study and connection | ZETDC reviews the effect on the network | Load-flow, short-circuit and protection studies, and the connection design |
| 4. PPA negotiation | Tariff, term, curtailment, termination, currency and payment security | Financial model, a legal adviser and the details of the guarantee package |
| 5. Proof of funding and interconnection agreement | The conditions you must meet before signing | Commitments for your own money (equity) and for loans (debt) |
| 6. Financial close and EPC | You meet the lenders' conditions and appoint the contractors | A technical file a bank will accept, and an independent engineer's report |
| 7. Build, commission, operate | Construction, testing, meeting the grid code, and starting to sell power | An owner's engineer, an operation and maintenance (O&M) contract and monitoring |
The government has also described a guarantee package to reduce risk for IPPs. It covers payment security, tariffs that reflect cost, and currency conversion. The terms differ from year to year. So we read the exact document in force when you sign.
What lenders and their engineers check
Banks and development finance institutions do not lend on a brochure. They hire an independent engineer to read your technical file. Expect questions in five areas:
- Energy yield. An independent assessment with P50 and P90 values. These are the energy you beat in 50% and 90% of years. It also covers yearly loss of output, uptime and other losses, using sunlight data that banks accept.
- Grid. A grid impact study that shows the plant can connect without breaking voltage, fault current or protection limits. It should also give an honest view of the risk of curtailment (being told to hold back) and outages on the network.
- Land and permits. Land title or lease, environmental approvals and other consents, with a timeline that matches the financial model.
- The buyer and the contracts. The PPA's payment terms, how well the buyer can pay, the guarantees and the currency of payment.
- Delivery risk. The EPC and O&M contracts, the warranties, the performance guarantees and the contractors' track record.
Where projects commonly stall
- Incomplete technical files that send the application back with questions. This costs months.
- Grid capacity. A site is chosen for its land and sun, then found to sit on a weak power line.
- PPA terms. Clauses on payment security, currency and curtailment that lenders will not accept as written.
- Development funding. You pay for studies, legal fees and permits years before any money comes in.
- Design drift after financial close. Contractors swap equipment or layouts, and no engineer on the owner's side checks.
How AVEX GRID helps
- Bankable feasibility study: the yield, layout, model and the technical sections that lenders and ZERA read.
- Grid-impact studies: load flow, short circuit and protection coordination in ETAP, with the connection design.
- Licence and PPA technical support: the technical schedules, the performance definitions, and a review of the curtailment and uptime clauses.
- Owner's engineer: design review, factory and site testing, commissioning and handover, on your side of the table with the contractor.
What AVEX GRID can take off your hands
AVEX GRID is an engineer-led energy consultancy in Zimbabwe. We do the technical work that turns an energy investment into a plant that is licensed, connected, financed and performing, whether you are a local operator or an investor overseas.
We quote fixed prices after a free scoping call and reply the same working day.
Frequently asked questions
How long does it take to get a solar IPP licensed in Zimbabwe?
It varies a lot. One 100 MW project took more than two years to get a licence before its PPA. A complete technical file and early talks with ZERA shorten the process.
Does a small solar plant need a licence?
Solar below 10 MW is still licensed by ZERA, but it pays no licence fee. AVEX GRID confirms the current position for your project as part of the scope.
Who buys the power?
For projects that connect to the grid, the buyer is ZETDC under a long-term PPA. Plants for your own use and private PPAs are also possible, under the licensing and wheeling rules.
What do lenders need from the technical side?
An independent yield assessment with P50 and P90 values, a grid impact study, proof of land and permits, the PPA terms, and a delivery plan with experienced contractors.
Sources and notes
General information to help you plan. The rules that apply to your site are confirmed by AVEX GRID against the current gazetted text, ZERA and ZETDC as part of the work. The sources used are listed below.
- Green Building Africa / SolarQuarter: Vungu Solar signs 25-year PPA with ZETDC for 30 MW project (Feb 2026)
- TaiyangNews: 100 MW solar energy PPA signed in Zimbabwe (Matshela Energy)
- AllAfrica: Landmark solar deal set to power Zimbabwe's energy future (June 2026)
- The Herald: ZERA licenses 440 MW power generation projects
- CleanTechnica: Zimbabwe looks to IPPs and rural minigrids (July 2025)
- The Herald: Energy sector reforms attract 1,000 MW additional power investments
- Bulawayo24: ZERA licensing report (majority of applications for own-consumption solar)